The Role of Integrated Project Management Techniques in Enhancing Infrastructure Project Performance in the Greater Cairo Metro

Hesham Sayed Seifelnaser Soliman1*
1 Department of Project Management, Faculty of Graduate Studies for Statistical Research, Cairo University, Giza, Egypt
* Corresponding author: Hesham Sayed Seifelnaser Soliman. Email: 12422023576587@pg.cu.edu.eg
International Scientific Technical and Economic Research 2026, Vol. 4, No. 4, pp. 1-44
DOI: 10.67541/istaer2628
Received: 12 August 2026; Revised: 27 August 2026; Accepted: 19 September 2026; Published: 16 October 2026
Abstract

Infrastructure projects frequently encounter challenges related to cost overruns, schedule delays, scope deviations, and quality deficiencies, particularly in complex rehabilitation projects operating under strict operational constraints. This paper investigates the Impact of Integrating Project Management Techniques on Improving the Performance of Infrastructure Projects, with an application to Greater Cairo Metro. A quantitative descriptive-analytical approach was adopted using data collected through a structured questionnaire from 242 valid respondents drawn from a population of 650 participants involved in the Fire Protection System Rehabilitation Project on Greater Cairo Metro Line 1. The data were analyzed using the Statistical Package for the Social Sciences (SPSS) 25 and Analysis of Moment Structures (AMOS) through reliability and validity tests, Confirmatory Factor Analysis (CFA), Structural Equation Modeling (SEM), and Path Analysis. The results revealed a statistically significant positive effect of integrating project management techniques on infrastructure project performance. The findings also demonstrated statistically significant positive effects for each of the four techniques investigated individually. Among the standardized path coefficients, Earned Value Management (EVM) had the numerically largest coefficient, followed by Program Evaluation and Review Technique (PERT), Six Sigma, and Work Breakdown Structure (WBS). The integrated application of these complementary techniques was associated with improvements in budget control, schedule adherence, scope adherence, and quality improvement. This study contributes by empirically examining both the overall integrated relationship and the individual relationships of EVM, WBS, PERT, and Six Sigma with infrastructure project performance within a real-world infrastructure rehabilitation project and provides practical guidance for improving the performance of similar projects operating under safety and operational constraints.

Keywords
Earned Value Management Six Sigma Work Breakdown Structure Program Evaluation and Review Technique Infrastructure Rehabilitation
References
  1. Lukhele, T. M., Botha, B., & Mbanga, S. (2022). A conceptual framework for systematic project planning towards the successful delivery of infrastructure development projects in the public sector. Journal of Public Administration, 57(3). DOI: 10520/ejc-jpad-v57-n3-a9
  2. Fauzan, M., & Sunindijo, R. Y. (2021). Lean construction and project performance in the Australian construction industry. IOP Conference Series: Earth and Environmental Science, 907(1), 012024. DOI: 10.1088/1755-1315/907/1/012024
  3. Bushuiev, D., & Kozyr, B. (2020). Hybrid infrastructure project management methodologies. Innovative Technologies and Scientific Solutions for Industries, 1(11), 35–43. DOI: 10.30837/2522-9818.2020.11.035
  4. Gemino, A., Reich, B. H., & Serrador, P. M. (2021). Agile, traditional, and hybrid approaches to project success: Is hybrid a poor second choice? Project Management Journal, 52(2), 161–175. DOI: 10.1177/8756972820973082
  5. Chountalas, P. T., & Tepaskoualos, F. A. (2019). Selective integration of management systems: A case study in the construction industry. The TQM Journal, 31(1), 12–27. DOI: 10.1108/TQM-03-2018-0028
  6. McDermot, E., Agdas, D., Rodríguez Díaz, C. R., Rose, T., & Forcael, E. (2022). Improving performance of infrastructure projects in developing countries: An Ecuadorian case study. International Journal of Construction Management, 22(13), 2469–2483. DOI: 10.1080/15623599.2020.1797985
  7. Andrić, J. M., Mahamadu, A.-M., Wang, J., Zou, P. X. W., & Zhong, R. (2019). The cost performance and causes of overruns in infrastructure development projects in Asia. Journal of Civil Engineering and Management, 25(3), 203–214. DOI: 10.3846/jcem.2019.8646
  8. Love, P. E. D., Sing, M. C. P., Ika, L. A., & Newton, S. (2019). The cost performance of transportation projects: The fallacy of the Planning Fallacy account. Transportation Research Part A: Policy and Practice, 122, 1–20. DOI: 10.1016/j.tra.2019.02.004
  9. Khan, A., Waris, M., Panigrahi, S., Sajid, M. R., & Rana, F. (2021). Improving the performance of public sector infrastructure projects: Role of project governance and stakeholder management. Journal of Management in Engineering, 37(2). DOI: 10.1061/(asce)me.1943-5479.0000886
  10. Abbas, D. B. (2023). The use of (PERT and CPM) techniques to analyze a project network (An applied study on Al-Mustafa complex construction project in Al-Hartha District). The Gulf Economist, 57, 229–296.
  11. Vazquez, A., Pozzana, I., Kalogridis, G., & Ellinas, C. (2023). Activity networks determine project performance. Scientific Reports, 13, 509. DOI: 10.1038/s41598-022-27180-0
  12. Ismail, I., Khan, A., Waris, M., Haron, H., & Simamora, B. H. (2021). Exploring the role of project governance and stakeholder management in public sector infrastructure projects. International Journal of Organizational Business Excellence, 2(1), 1–10. DOI: 10.21512/ijobex.v2i1.7141
  13. Daoud, A. O., El Hefnawy, M., & Wefki, H. (2023). Investigation of critical factors affecting cost overruns and delays in Egyptian mega construction projects. Alexandria Engineering Journal, 83, 326–334. DOI: 10.1016/j.aej.2023.10.052
  14. Gonçalves-Dosantos, J. C., García-Jurado, I., & Costa, J. (2020). Project Management: An R package for managing projects. The R Journal, 12(1), 419–436. DOI: 10.32614/rj-2020-009
  15. Ba'Its, H. A., Arum Puspita, I., & Bay, A. F. (2020). Combination of Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) for Project Schedule Development. International Journal of Integrated Engineering, 12(3), 68–75. DOI: uthm/ijie/4207
  16. Ou-Yang, C., & Chen, W.-L. (2019). A hybrid approach for project crashing optimization strategy with risk consideration: A case study for an EPC project. Mathematical Problems in Engineering, 2019, Article 9649632. DOI: 10.1155/2019/9649632
  17. Zohrehvandi, S. (2022). A project-scheduling and resource management heuristic algorithm in the construction of combined cycle power plant projects. Computers, 11(2), Article 23. DOI: 10.3390/computers11020023
  18. Taguedda, K., & Daoui, C. (2023). Contributions of network analysis to the effectiveness of project management: Case study of public works sector in Tamangasset. Journal of Strategy and Development, 13(2), 10–32. DOI: 10.34276/1822-013-002-001
  19. Aramali, V., Gibson, G. E., El Asmar, M., & Cho, N. (2021). Earned Value Management System State of Practice: Identifying Critical Subprocesses, Challenges, and Environment Factors of a High-Performing EVMS. Journal of Management in Engineering, 37(4), Article 0000925. DOI: 10.1061/(ASCE)ME.1943-5479.0000925
  20. Nizam, A., & Elshennawy, A. (2019). Review of earned value management (EVM) methodology, its limitations, and applicable extensions. Journal of Management & Engineering Integration, 12(1), 59–70. DOI: 10.62704/10057/24251
  21. Song, J., Martens, A., & Vanhoucke, M. (2022). Using earned value management and schedule risk analysis with resource constraints for project control. European Journal of Operational Research, 297(2), 451–466. DOI: 10.1016/j.ejor.2021.05.036
  22. Elghandour, A., Eid, A. F., & El Daly, H. (2021). Improving performance of construction projects by integrating risk into earned value management: A literature review. Journal of Al-Azhar University Engineering Sector, 16(60), 833–850. DOI: 10.21608/auej.2021.187983
  23. Abu El-Maaty, A. E., Akal, A. Y., & El-Hamrawy, S. A. K. (2018). The iron triangle of projects management: Quality, schedule and cost of road infrastructure projects in Egypt. In J. Calautit, F. M. S. Al-Zubaidi, A. A. Alshawa, & A. A. Al-Atabi (Eds.), Towards Sustainable Cities in Asia and the Middle East (Sustainable Civil Infrastructures, pp. 1–14). Springer. DOI: 10.1007/978-3-319-61645-2_1
  24. Johari, N. F., Zainal, R., Kasim, N., & Musa, S. M. S. (2024). The study of Six Sigma practices in construction project management performance. Research in Management of Technology and Business, 5(1), 1179–1205. DOI: uthm/rmtb/15968
  25. Makibelo, P., Makhanya, B., & Nel, H. (2021). Implementation of Six Sigma as quality improvement in a South African municipality. In Proceedings of the International Conference on Industrial Engineering and Operations Management (Monterrey, Mexico, November 3–5, 2021, pp. 1426–1438). IEOM Society International. DOI: ieomsociety/2021monterrey/229
  26. Shumali, S. I., & Nassar, A. J. (2021). The impact of implementing project management knowledge areas on public project quality in Palestine. Noor Economic Studies Journal, 6(2), 1–21. DOI: asjp.cerist.dz/151826
  27. Kaufmann, C., & Kock, A. (2022). Does project management matter? The relationship between project management effort, complexity, and profitability. International Journal of Project Management, 40(6), 624–633. DOI: 10.1016/j.ijproman.2022.05.007
  28. Al Amoudi, G. M., Hassan, A. F. A. H. M., & Jarad, F. A. (2024). The role of international standards for project management in increasing project quality in application to international partnerships in the kingdom of Saudi Arabia. International Journal of Financial, Administrative and Economic Sciences, 3(9). DOI: 10.59992/IJFAES.2024.v3n9p1
  29. Kebede Legesse, A., Abera, B., & Mekonnin, A. (2024). Effects of project management practices on the performance of Ethiopian National Stadium. Ethiopian Journal of Sport Science, 5(1), 19–42. DOI: 10.5281/zenodo.14531811
  30. Albtoush, A. M. F., Doh, S. I., Rahman, R. A., & Al-Momani, A. H. (2022). Critical success factors of construction projects in Jordan: An empirical investigation. Asian Journal of Civil Engineering, 23, 1087–1099. DOI: 10.1007/s42107-022-00470-8
  31. Sweis, R. J., & Jaradat, M. (2022). Project management performance of construction projects in Jordan: A comparative study of ISO 9001-certified and non-certified companies. The TQM Journal, 34(5), 1341–1364. DOI: 10.1108/TQM-02-2021-0060
  32. Safapour, E., & Kermanshachi, S. (2022). Key components in schedule development of post-disaster reconstruction projects. In Construction Research Congress 2022 (pp. 48–56). American Society of Civil Engineers. DOI: 10.1061/9780784483954.006
  33. Ateş, B., & Eirgash, M. A. (2025). Proactive and data-driven decision-making using earned value analysis in infrastructure projects. Buildings, 15(14), 2388. DOI: 10.3390/buildings15142388
  34. Kline, R. B. (2011). Principles and practice of structural equation modeling (3rd ed.). Guilford Press. DOI: 10.1002/0470013192.bsa655
  35. Hair, J. F., Hult, G. T. M., Ringle, C. M., & Sarstedt, M. (2014). A primer on partial least squares structural equation modeling (PLS-SEM). Springer. DOI: 10.1080/1743727X.2015.1005806
  36. Thompson, S. K. (2012). Sampling (3rd ed.). Wiley.
  37. Joshi, A., Kale, S., Chandel, S., & Pal, D. K. (2015). Likert scale: Explored and explained. British Journal of Applied Science & Technology, 7(4), 396–403. DOI: 10.9734/BJAST/2015/14975
  38. Hair, J. F., Anderson, R. E., Tatham, R. L., & Black, W. C. (1998). Multivariate data analysis (5th ed.). Prentice Hall.
  39. Byrne, B. M. (2001). Structural equation modeling with AMOS: Basic concepts, applications, and programming. Lawrence Erlbaum Associates Publishers. DOI: 10.4324/9780203805534
  40. El-Sheikh, A. A., Abonazel, M. R., & Gamil, N. (2017). A review of software packages for structural equation modeling: A comparative study. Applied Mathematics and Physics, 5(3), 85–94. DOI: 10.12691/amp-5-3-2